| Weekly Construction Calendar |
| Tuesday, September 7: |
- Electricians: 1817 W. Ormsby rough in
- Dismas: TBA
- Knoblock: 2211 Woodland grade back yard for shed placement; 844 S. 37th p/u broken concrete
- AmeriCorps Garth/Ben: Orientation
|
| Wednesday, September 8: |
- Chuck's Team: 3016 Bank complete walls;1227 S. Clay install tile
- Dismas: TBA
- Framing Crew: 3016 Bank pour porches; 540 Caldwell form porches
- Holm Team: 2722 Greenwood drywall
- Paint Crew: 2722 Greenwood shed
- Trim Crew: 321 S. 42nd lauan
- AmeriCorps Garth/Ben: Orientation
- Ron out pm
|
| Thursday, September 9: |
- Chuck's Team: 1227 S. Clay install tile; 321 S. 42nd gutters; 3016 Bank deliver walls
- Dismas: TBA
- Dream Machine: 844 S. 37th framing
- Framing Crew: 540 Caldwell pour porches; 2211 Woodland form flatwork
- Holm Team: 2722 Greenwood drywall, porch rails
- Richey: 1827 Gaulbert siding
- Trim Crew: 2342 W. Madison kitchen cabinets
- Veech/Women for Habitat: 2342 W. Madison interior trim
- AmeriCorps Garth/Ben: Orientation
|
| Friday, September 10: |
- Coakley w/Dismas: 3312 W. Kentucky demo
- Dismas: 3312 W. Kentucky demo
- Dream Machine w/Hyatt Regency: 2211 Woodland build shed; 844 s. 37th framing
- Framing Crew: 1227 S. Clay form flatwork
- Layout Crew: TBA
- Richey: 1827 Gaulbert framing, siding
- AmeriCorps Garth/Ben: Orientation
|
| Saturday, September 11: |
- Chuck's Team: 1227 S. Clay interior trim
- Coakley: 3312 W. Kentucky demo
- Dismas:
- Dream Machine: 844 S. 37th framing, siding
- Landscaping: 2211 Woodland
- M&M w/UofL: 540 Caldwell move walls
- St. Matthews: TBA
- St. Xavier Club: TBA
- UofL: 540 Caldwell move walls to site
- Veech/Women for Habitat: 2342 W. Madison interior trim
- AmeriCorps Garth/Ben: Orientation
|