Weekly Construction Calendar
Tuesday, September 7:
  • Electricians: 1817 W. Ormsby rough in
  • Dismas: TBA  
  • Knoblock: 2211 Woodland grade back yard for shed placement; 844 S. 37th p/u broken concrete
  • AmeriCorps Garth/Ben: Orientation 
Wednesday, September 8:
  • Chuck's Team: 3016 Bank complete walls;1227 S. Clay install tile 
  • Dismas TBA
  • Framing Crew: 3016 Bank pour porches; 540 Caldwell form porches 
  • Holm Team: 2722 Greenwood drywall
  • Paint Crew: 2722 Greenwood shed 
  • Trim Crew: 321 S. 42nd lauan
  • AmeriCorps Garth/Ben: Orientation
  • Ron out pm  
Thursday, September 9:
  • Chuck's Team: 1227 S. Clay install tile; 321 S. 42nd gutters; 3016 Bank deliver walls 
  • Dismas: TBA
  • Dream Machine: 844 S. 37th framing
  • Framing Crew: 540 Caldwell pour porches; 2211 Woodland form flatwork 
  • Holm Team: 2722 Greenwood drywall, porch rails  
  • Richey: 1827 Gaulbert siding
  • Trim Crew: 2342 W. Madison kitchen cabinets 
  • Veech/Women for Habitat: 2342 W. Madison interior trim 
  • AmeriCorps Garth/Ben: Orientation 
Friday, September 10:
  • Coakley w/Dismas: 3312 W. Kentucky demo 
  • Dismas: 3312 W. Kentucky demo 
  • Dream Machine w/Hyatt Regency:  2211 Woodland build shed; 844 s. 37th framing 
  • Framing Crew: 1227 S. Clay form flatwork 
  • Layout Crew: TBA 
  • Richey: 1827 Gaulbert framing, siding
  • AmeriCorps Garth/Ben: Orientation  
Saturday, September 11:
  • Chuck's Team: 1227 S. Clay interior trim
  • Coakley: 3312 W. Kentucky demo
  • Dismas:
  • Dream Machine: 844 S. 37th framing, siding
  • Landscaping: 2211 Woodland
  • M&M w/UofL: 540 Caldwell move walls
  • St. Matthews: TBA
  • St. Xavier Club: TBA
  • UofL: 540 Caldwell move walls to site 
  • Veech/Women for Habitat: 2342 W. Madison interior trim
  • AmeriCorps Garth/Ben: Orientation